Drax plans £20bn AI data centre at UK's largest power station
Drax, Brookfield and Radiant want to build an AI data centre in North Yorkshire that could reach more than 1GW, with total investment possibly topping £20bn.

Drax plans to build an AI data centre at its North Yorkshire power station, Britain's largest, together with Brookfield and Radiant, Brookfield's UK-based AI infrastructure business. The site could eventually host more than 1GW of computing capacity, Drax said in a stock market statement on Tuesday.
Brookfield estimates total investment could exceed £20bn ($26.8bn), chips included. An initial £2.5bn would fund a first phase of up to 100MW, targeted from early 2028. The money would flow through a joint venture between Brookfield and Qai, a subsidiary of the Qatar Investment Authority.
Three phases, with power generated on site
The estate covers more than 1,000 acres, with about 4GW of grid access and 2.6GW of generating capacity. Phase one would draw on the national grid. Phase two aims to add 500MW between 2028 and 2031, this time powered directly by Drax's own generators under a long-term contract. A third phase would add capacity after 2031.
That depends on government consent. Drax's subsidy contract for biomass power runs from April 2027 to March 2031 and lets it ask to send up to 500MW to a data centre. The government and the Low Carbon Contracts Company would decide, weighing consumer value, energy security and sustainability. "Drax Power Station is one of the few UK sites that can provide large-scale reliable power directly to data centre customers," said CEO Will Gardiner.
The first phase still needs planning permission, regulatory and grid approvals, a tenant and a final investment decision from each partner. Radiant will seek anchor customers before construction. Drax expects a public consultation to begin this month, and the partners plan a voluntary fund for nearby communities.
Why it matters
Long grid queues have delayed other UK data centre projects, and operators say power and labour are now their bottleneck. Drax burns wood pellets and supplies almost 5% of UK electricity, but the government has said it will play a "much more limited role" in future, with subsidies halved from 2027 to 2031. An earlier bid to make the site an AI Growth Zone was rejected by the government.
Chief Secretary to the Treasury Emma Reynolds said such investments would help pave the way to a new age of British reindustrialisation, creating jobs in Yorkshire.
Apps worth a look
Tap the right tiles, add them up, hit the target. Easy to learn, hard to master. Free, for all ages.
Talk to an AI conversation partner; every sentence comes back corrected and explained in your language. 9 languages, A1 to C2.
Open EDIFACT and X12 messages, see every segment explained, convert to JSON/XML, export PDF and Excel. Runs locally, no upload.
Pick who it is for, the occasion and their personality. The search engine reads product descriptions from local shops and ranks what fits. Free, no sign-up.
More from this day
See all →
Elvis Presley Rights Holders Sue Anthropic Over Claude Lyrics

Revolut Makes Z.ai's GLM Its Default Coding AI for 2,000 Engineers

Wiki.js 3.0 Released: Rewrite Adds Real-Time Editing

Raven Prism: Linux-Based AI Glasses Head to Market at a Luxury Price
More in: Business
See all →
Generali Takes Over Redclick Portfolio as Genertel Exits Poland

Data Centers Turn to Converted Jet Engines for AI Power

SK Telecom Launches AI Data Center Units SK Hyper, SK Horizon