Adif invested €4.7bn in 2025, but only €437m kept high-speed rail running
Adif executed €4.696 billion in investment in 2025, yet high-speed maintenance received just €437 million. Adjusted for inflation and network value, spending per asset has fallen.

Spain's rail infrastructure manager Adif executed €4.696 billion in investment in 2025, far above the €1.707 billion spent on high-speed investment in 2019. But only €437 million of that went to maintaining the high-speed network, a gap that has taken on new weight after two fatal accidents on the Madrid-Sevilla line in under a year.
The crashes at Adamuz (Córdoba) and Urda (Toledo) have left more than a hundred people dead, making this the worst year in the history of Spanish high-speed rail.
Maintenance has grown, but less than it seems
In 2018, Adif and Adif Alta Velocidad spent €727 million on maintenance; in 2025 the figure was €1.12 billion. Spending specific to high-speed rail rose from €255 million to €437 million. Adjusted for inflation, however, the 2018 amounts equal about €932 million and €326.91 million respectively, so real growth is much smaller than the headline numbers suggest.
The network has also grown. Its asset value rose from €44.743 billion in 2018 to €51.449 billion today. Combining inflation, spending and asset value, maintenance spending per unit of asset value in high-speed rail is about 13% lower. Per kilometre, the picture is similar: Geotren data put 2005 spending at €116,329 per km, or about €183,920 in today's money, against roughly €110,000 last year.
The Transport Ministry published charts showing maintenance growth, but they refer to the "rail network" in general and do not break out high-speed spending.
More traffic, ageing track
In Europe, Spain ranks near the bottom for the share of investment devoted to maintenance: 15%, against 34% in France. Only Denmark and Slovakia spend proportionally less, although comparisons are difficult because network structures differ.
Traffic is also far heavier. Former transport minister Óscar Puente noted that 289 trains now run between Madrid and Sevilla, compared with six a day in the 1990s, on track that is around 30 years old. When the LZB safety system failed on 30 October, six trains stopped at once on a stretch of under 70 kilometres.
Traffic controllers say staffing is unchanged since liberalisation and criticise night-time works instead of line closures for renewal. They argue ERTMS suffers fewer incidents than LZB, though drivers rate the two as comparable for safety. The debate now also covers whether the high-speed network has been expanded too far under regional pressure.
Apps worth a look
Tap the right tiles, add them up, hit the target. Easy to learn, hard to master. Free, for all ages.
Talk to an AI conversation partner; every sentence comes back corrected and explained in your language. 9 languages, A1 to C2.
Open EDIFACT and X12 messages, see every segment explained, convert to JSON/XML, export PDF and Excel. Runs locally, no upload.
Pick who it is for, the occasion and their personality. The search engine reads product descriptions from local shops and ranks what fits. Free, no sign-up.
More from this day
See all →
GOG GALAXY Is Coming Natively to Linux After 18 Years
Claude Code accused of leaking users' email addresses to websites

Alta Ares wins six NATO counter-drone lots in first big deal

NCBR Sets Aside PLN 25 Million for International AI R&D Projects
More in: Business
See all →
Poland's Palantir Defence Deal Draws Calls for Risk Audit

S3NS adds managed AI services to Premi3ns with Mistral, Google models

Moscow Court Orders Ex-Google Russia Chief to Pay 160 Billion Rubles