Coriscada wind farm: 4 turbines replace 40 and make 78% more power

In Galicia, Endesa is swapping 40 wind turbines from 1998 for just four modern ones. The same grid limit applies, yet output should jump by 78.5%.

Wind turbines on a hillside in Galicia, northwest Spain, where the Coriscada wind farm is being rebuilt.
Image: Frandroid

Forty wind turbines out, four in. That is the plan at the Coriscada wind farm in Galicia, northwest Spain, and it shows how far the technology has moved in about 28 years.

The farm, run by Endesa in the municipalities of Mañón and Ortigueira, went up in 1998. Its 40 turbines add up to 24 MW and produce close to 47 GWh a year. Endesa started the modernisation at the end of September. The new setup will be four machines of 7 MW each, so 28 MW installed. The power fed into the grid stays capped at 24 MW, as before.

The gain comes from how the new turbines behave in weak wind. According to Endesa, annual production should rise by 78.5% to almost 84 GWh.

How long will the Coriscada repowering take?

The work, led by Endesa's subsidiary Enel Green Power España, runs through 2027. Tests of the new machines are planned for late 2027, with full operation in March 2028. Endesa is spending 36.3 million euros, up to 6.79 million of it public aid from IDAE, Spain's energy agency, under the recovery plan.

What is wind farm repowering?

Repowering means keeping a site productive by replacing the turbines entirely. Not just the blades: towers and foundations too. Only the grid connection usually stays, unless something specific needs work.

It is becoming common in Spain, an early renewables pioneer. In 2025 alone, seven farms were rebuilt, with 20 turbines replacing 147, according to the wind industry association AEE. Its 2026 yearbook says 9.77 GW of Spain's 32.9 GW of wind capacity has been running for over 20 years. Spain's ecological transition ministry expects 10 to 12 GW to be renewed by 2030. Coriscada is not the first: at Aldeavieja in Ávila, 22 turbines totalling 14.52 MW gave way to four machines totalling 24 MW.

The old turbines will not be scrapped, Endesa says. Some become spare parts for other sites in the group, some are resold, and whatever cannot be reused will be recovered as material.

Apps worth a look

SUMO: the number puzzle

Tap the right tiles, add them up, hit the target. Easy to learn, hard to master. Free, for all ages.

Tags:wind powerrepoweringendesaspainrenewable energycoriscada

More from this day

See all →

More in: Science

See all →