Norway pauses new data centre grid connections as requests hit 31 GW
Norway's grid operator Statnett has stopped taking new data centre connection reservations. Requests now add up to 31.3 GW, more than the country's 25 GW peak demand.

Norway has so many data centre requests that they would use more electricity than the whole country does at its busiest. So the grid operator has hit pause.
On 9 November 2026, Statnett stopped accepting new reservations for data centre connections to the transmission grid. Facilities already connected and projects already approved are not affected. The company expects to reopen reservations by 1 August 2027 at the latest.
The numbers explain why. Connected data centres currently total about 800 MW. Reservations already made come to 4.2 GW, another 9.1 GW is in the queue, and requests for a further 18 GW are waiting. That is 31.3 GW of new demand, against a national peak demand of 25 GW. Not every project will get built, but the scale is hard to ignore.
There is also the question of how data centres behave. According to Statnett, their power use can swing sharply within a short time because it is controlled by software, and they are sensitive to disturbances on the grid. That makes them different from traditional large industrial customers.
What is Norway doing about data centres?
The government plans to make data centres subject to a permit. Digitalisation minister Torgeir Michaelsen said Norway needs data centres, but not every kind, and that growth must be managed so the country gets the ones that benefit society most. Priority would go to facilities supporting defence, police, healthcare, telecoms and finance. Last year the government also floated a temporary ban on new crypto-mining data centres.
Part of the motive is the thin payback. An independent body advising the government said last month that 90% of the country's data centre capacity is foreign-owned. Once built, the sites create few jobs, and little of the revenue stays in Norway.
Norway is already home to data centres run by Microsoft, TikTok and CoreWeave, with many more planned. Cheap hydropower and a cool climate make it an obvious choice, which is exactly the problem.
Apps worth a look
Tap the right tiles, add them up, hit the target. Easy to learn, hard to master. Free, for all ages.
Talk to an AI conversation partner; every sentence comes back corrected and explained in your language. 9 languages, A1 to C2.
Open EDIFACT and X12 messages, see every segment explained, convert to JSON/XML, export PDF and Excel. Runs locally, no upload.
Pick who it is for, the occasion and their personality. The search engine reads product descriptions from local shops and ranks what fits. Free, no sign-up.
More from this day
See all →
Comet 220P/McNaught suddenly got 1,000 times brighter. Here's why

Coral Hart used AI to write 370 books in 20 months

WhatsApp Zaps: self-deleting photos and videos for any chat

Green SM taxis: Karnataka halts new registrations, eyes mandatory meters
More in: Business
See all →
Chase outage: Zelle and bank transfers delayed across the US

Stand with Jensen: 175,000 sign letter to bring Huang back to Nvidia

Sentinel AI webcam monitoring: photo every 3 minutes, then a lawsuit